Tower chute replacement
Renders
Manufacturing
To minimise production disruption at a coal export terminal, it was decided that a distribution tower requiring remedial work would be replaced entirely. The client took advantage of the opportunity to also upgrade the original one to two transfer system components, including incorporating online switching and splitting capability and provision for a future third discharge stream.
Modifications included conveyor alignment, pulley, and gravity take-up location changes to optimise the material flow path through the tower. The new chute work features an advanced head chute and fines collection design, discharging into a diversion sub-assembly.
In line with a rapid removal and installation strategy, the new tower components were manufactured and assembled to the extent practical (including chute component) and located adjacent to the existing tower for lifting into position as preassembled floors.
Before the first-floor level of the tower was installed onto its foundations, the MHOI designed and shop-assembled skirting assemblies that were lifted into position onto the receiving conveyor as preassembled modules.